BEACH FILL SCHEDULED TO BEGIN WEDNESDAY IN AVALON

Avalon 22nd Street BeachA beach fill project should begin on Wednesday in Avalon. Officials are ready for the backpassing project to start and should be complete by March 15. It is anticipated that sand will be relocated from the 60th Street to 71st Street beachfront between February 1st -29th; Sand will be relocated from the 32nd Street to 38th Street beachfront between March 1st-14th. The backpassing project will result in the mechanical relocation of sand that has naturally accreted to the southern beaches to the north end of the beachfront.